Warehouse complex, Moscow, Russia
Facts & Figures
Genset/engine: | 3 x TCG 2020 V16 |
Segment/gas type: | Natural gas |
Customer: | Vertikal JSC |
Contractor: | NEUHAUS |
Total output: | 4.68 MWel / 4.68 MWth |
Commissioning: | 2018 |
The 4.5 MW CHP plant designed to provide electricity and heat to the to the warehouse premises in Moscow was put into operation by NEUHAUS, the official MWM distributor in Russia. The power plant consists of original MWM containers with heat recovery system. To avoid additional costs for foundation and freestanding pipe constructions, the exhaust pipes were raised up to 17 m and mounted to the container base. The power plant is operated in an island mode.