Torres de Segre, Spain
Facts & Figures
Genset / Engine: | 2x TCG 2020 V12 |
Segment / Fuel Type: | Power only / Fuel Blending Biogas and Natural Gas |
Customer / Operator: | CES Spanien |
Total output: | 2.4 MWel |
Installation / Commissioning: | February 2013 |
The plant located in Torres de Segre consists of two TCG 2020 V12 containerized gensets producing electricity and providing heat for the operation of the fermenter. The system allows an operation with biogas as well as an uninterrupted switch to fuel blending biogas and natural gas. Fuel blending enables a continuous operation even when biogas production is reduced.