Logistics Centre, Penza, Russia
Facts & Figures
Genset/engine: | 1 х TCG 2020 V16K |
Segment/gas type: | Natural gas |
Customer: | Tander JSC |
Contractor: | Valdex Energetika LLC |
Total output: | 1.5 MWel / 1.7 MWth |
Commissioning: | 2017 |
Specialists of Valdex Energetica implemented a project of a power plant based on a MWM gas genset TCG 2020 V16K with electric capacity of 1500 kW, voltage of 10.5 kW, and a heat recovery system with thermal power of up to 1712 kW at 100% load. The power plant is based on modern European gas equipment produced by leading manufacturers. The overall efficiency is 87.6%. It is operated all year-round, round-the-clock, in island and combined mode in parallel with an external grid without cross flows. The power plant provides an uninterrupted all-year-round power supply and is operated in island mode in parallel with other gensets.